Expired
Milestone
Mar 23, 2021–May 1, 2021
signalc mvp
objective
- release signalboost + signalc to public during mozfest (3/8 - 3/22)
requirements
- feature parity w/ signalboost + signald
- acceptable & communicable message lag
- acceptable & communicable crash rate & recovery speed
- acceptable & communicable max capacity
benchmarks
- define "acceptable message lag"
- define "acceptable" crash rate & recovery speed
- define "acceptable max capacity"
missing specs:
- measuring max capacity
- measuring crash recovery
status
===> BOARD <===
- points: 35
- complete: 0
- left: 35
- time: 5 weeks
- spent: 0
- left: 5
- burn rate:
- current: n/a
- needed: 7pts/wk
- projections:
- 3pts/wk -> 12 weeks
- 8pts/wk -> 4.5 weeks